ARC Active Projects

October 29, 2008

 

Updates since the latest meeting October 29, 2008 are indicated in bold. Postings of new projects for review are being placed by the 12th of the month in the Community Informational Holders at each gate location as well as some additional holders within several Subdivisions of the Community. This information is also available on the La Reserve Website.

 

The following projects are currently under review as of October 29, 2008:

                Lot 12     Wilderness Estates I                           final plans approved 10-29-08

                Lot 13     Wilderness Estates I                           ongoing home construction projects

                Lot 23    Wilderness Estates I                          completed post construction compliance 10-06-08

                Lot 27     Wilderness Estates II                          Resident occupied/completed post construction compliance inspection

                Lot 30     Wilderness Estates II                          final plans approved 01-01-06/pending preconstruction meeting

                Lot 33     Wilderness Estates II                          Resident occupied/completed post construction compliance inspection

                Lot 38     Wilderness Estates II                          final plans approved July 2007 for garage/carriage house & outdoor areas                                                                                                                              including pool

                Lot 17     Wilderness Estates III                         preconstruction meeting 10-25-06/post construction compliance                                                                                                                               inspection agreement determined 09-29-08

                Lot 34     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 36     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 51     Wilderness Estates III                         preliminary plans approved 08-27-08               

                Lot 52     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 4T    Wilderness Estates III                         preliminary plans approved September 2007

                Desert Point Retirement Center                         completed post construction compliance inspection 10-01-08

 

The following projects have been removed from New Construction Activity/remaining deposits have been refunded:

                Lot 3       Wilderness Estates I                           final plans approved 11-01-06

                Lot 42     Wilderness Estates II                          preliminary plans approved December 2006

                Lot 14     Wilderness Estates III                         modified preliminary plans approved 01-09-08

                Lot 56     Wilderness Estates III                         preliminary plans approved September 2005

 

Jamie Hanson is the new Administrative Assistant to La Reserve and will receive and coordinate items to be reviewed by the LRCA Architectural Committee. Any questions regarding this process should be directed to her at the Management Office.

 

Grant Parker of Design Review Administrators, LLC has been contracted by the La Reserve Community Association to serve as the provider of design review and construction compliance services throughout the Community. He will also be assisting the Architectural Committee with large alterations, additions, and improvements.

 

It is important to note the amount of time that evolves from submittal to the beginning of new construction varies. While postings of projects for review are timely, from approval of final plans, permits obtained from the Town of Oro Valley, to the preconstruction meeting, months have passed. While all the requirements are specifically explained at the preconstruction meeting, issues will arise. Any conflicts should be directed to Dick Holloway, Controlled Access Manager and Construction Site Supervisor through the LRCA Management Office or Gatehouse Attendant.

 

Construction continues on the initial seven units by Pusch Ridge Properties, LLC, in the development of the 49 Mirabella Villas along Pusch Wilderness Drive. Review of architectural details and the Pusch Wilderness Drive interface are ongoing with the Committee. The Mirabella entryway and signage located beyond the North Gate was reviewed by the Committee and has since been completed.  New Subdivision Signage approved for the easternmost beginning of property for sale purposes.

 

The ongoing development of the 237 acres of property known as Ponticello, beyond the North Gate across the bridge by Jack Schoof, Electronic Communities/Benchmark Homes continues. In January 2007, the Committee reviewed conceptual plans for the entry to the bridge; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions. Again in July 2008, the Committee reviewed conceptual plans for additions to the entryway including signage to Ponticello; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions.

 

The stone veneer proposed for the exterior of the North Gatehouse was approved to compliment already existing stonework and application at this location.

 

Discussion pertaining to the Revised Plant List took place at the January 9th, 2007 LRCA Residents’ Council Meeting. Responses from the Community were received and additional details were worked on by La Reserve Residents and the LRAC. The Revised Plant List was approved by the LRCA Board of Directors at the May 19, 2008 Meeting. The Listing will be posted to the La Reserve Websites and incorporated into the LRCA Design Guidelines.

 

 

 

 

September 24, 2008

 

Updates since the latest meeting September 24, 2008 are indicated in bold. Postings of new projects for review are being placed by the 12th of the month in the Community Informational Holders at each gate location as well as some additional holders within several Subdivisions of the Community. This information is also available on the La Reserve Website.

 

The following projects are currently under review as of September 24, 2008:

                Lot 12     Wilderness Estates I                           preliminary plans approved 04-30-08

                Lot 13     Wilderness Estates I                           ongoing home construction projects

                Lot 27     Wilderness Estates II                          Resident occupied/completed post construction compliance inspection

                Lot 30     Wilderness Estates II                          final plans approved 01-01-06/pending preconstruction meeting

                Lot 33     Wilderness Estates II                          Resident occupied/completed post construction compliance inspection

                Lot 38     Wilderness Estates II                          final plans approved July 2007 for garage/carriage house & outdoor areas                                                                                                                              including pool

                Lot 17     Wilderness Estates III                         preconstruction meeting 10-25-06/awaiting post construction compliance                                                                                                               inspection

                Lot 34     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 36     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 51     Wilderness Estates III                         preliminary plans approved 08-27-08               

                Lot 52     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 4T    Wilderness Estates III                         preliminary plans approved September 2007

                Desert Point Retirement Center                         final plans approved for Phase 2 to the existing 3-story assisted living facility/51                                                                                 additional units added with improvements to the entry, parking, pool, and                                                                                                              common areas/preconstruction meeting 06-27-07/construction in final                                                                                                                     stages of completion

 

The following projects have been removed from New Construction Activity/remaining deposits have been refunded:

                Lot 3       Wilderness Estates I                           final plans approved 11-01-06/pending preconstruction meeting

                Lot 42     Wilderness Estates II                          preliminary plans approved December 2006

                Lot 14     Wilderness Estates III                         modified preliminary plans approved 01-09-08

                Lot 56     Wilderness Estates III                         construction postponed indefinitely/potentially 2008

 

Jamie Hanson is the new Administrative Assistant to La Reserve and will receive and coordinate items to be reviewed by the LRCA Architectural Committee. Any questions regarding this process should be directed to her at the Management Office.

 

Grant Parker of Design Review Administrators, LLC has been contracted by the La Reserve Community Association to serve as the provider of design review and construction compliance services throughout the Community. He will also be assisting the Architectural Committee with large alterations, additions, and improvements.

 

It is important to note the amount of time that evolves from submittal to the beginning of new construction varies. While postings of projects for review are timely, from approval of final plans, permits obtained from the Town of Oro Valley, to the preconstruction meeting, months have passed. While all the requirements are specifically explained at the preconstruction meeting, issues will arise. Any conflicts should be directed to Dick Holloway, Controlled Access Manager and Construction Site Supervisor through the LRCA Management Office or Gatehouse Attendant.

 

Construction continues on the initial seven units by Pusch Ridge Properties, LLC, in the development of the 49 Mirabella Villas along Pusch Wilderness Drive. Review of architectural details and the Pusch Wilderness Drive interface are ongoing with the Committee. The Mirabella entryway and signage located beyond the North Gate was reviewed by the Committee and has since been completed.

 

The ongoing development of the 237 acres of property known as Ponticello, beyond the North Gate across the bridge by Jack Schoof, Electronic Communities/Benchmark Homes continues. In January 2007, the Committee reviewed conceptual plans for the entry to the bridge; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions. Again in July 2008, the Committee reviewed conceptual plans for additions to the entryway including signage to Ponticello; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions.

 

The stone veneer proposed for the exterior of the North Gatehouse was approved to compliment already existing stonework and application at this location.

 

Discussion pertaining to the Revised Plant List took place at the January 9th, 2007 LRCA Residents’ Council Meeting. Responses from the Community were received and additional details were worked on by La Reserve Residents and the LRAC. The Revised Plant List was approved by the LRCA Board of Directors at the May 19, 2008 Meeting. The Listing will be posted to the La Reserve Websites and incorporated into the LRCA Design Guidelines.

 

 

 

 

July 30, 2008

 

Updates since the latest meeting July 30, 2008 are indicated in bold. Postings of new projects for review are being placed by the 12th of the month in the Community Informational Holders at each gate location as well as some additional holders within several Subdivisions of the Community. This information is also available on the La Reserve Website.

 

The following projects are currently under review as of July 30, 2008:

                Lot 12    Wilderness Estates I                          preliminary plans approved 04-30-08

                Lot 13     Wilderness Estates I                           ongoing home construction projects

                Lot 27     Wilderness Estates II                          preconstruction meeting 08-16-06/awaiting post construction compliance                                                                                                               inspection

                Lot 30     Wilderness Estates II                          final plans approved 01-01-06/pending preconstruction meeting

                Lot 33     Wilderness Estates II                          Resident occupied/completed post construction compliance inspection

                Lot 38     Wilderness Estates II                          final plans approved July 2007 for garage/carriage house & outdoor areas                                                                                                                              including pool

                Lot 17     Wilderness Estates III                         preconstruction meeting 10-25-06/awaiting post construction compliance                                                                                                               inspection

                Lot 34     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 36     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 52     Wilderness Estates III                         Resident occupied/completed post construction compliance inspection

                Lot 4T    Wilderness Estates III                         preliminary plans approved September 2007

                Desert Point Retirement Center                         final plans approved for Phase 2 to the existing 3-story assisted living facility/51                                                                                 additional units added with improvements to the entry, parking, pool, and                                                                                                              common areas/preconstruction meeting 06-27-07/ construction in final                                                                                                   stages of completion

 

The following projects have been removed from New Construction Activity/remaining deposits have been refunded:

                Lot 3       Wilderness Estates I                           final plans approved 11-01-06/pending preconstruction meeting

                Lot 42     Wilderness Estates II                          preliminary plans approved December 2006

                Lot 14     Wilderness Estates III                         modified preliminary plans approved 01-09-08

                Lot 56     Wilderness Estates III                         construction postponed indefinitely/potentially 2008

 

Jamie Hanson is the new Administrative Assistant to La Reserve and will receive and coordinate items to be reviewed by the LRCA Architectural Committee. Any questions regarding this process should be directed to her at the Management Office.

 

Grant Parker of Design Review Administrators, LLC has been contracted by the La Reserve Community Association to serve as the provider of design review and construction compliance services throughout the Community. He will also be assisting the Architectural Committee with large alterations, additions, and improvements.

 

It is important to note the amount of time that evolves from submittal to the beginning of new construction varies. While postings of projects for review are timely, from approval of final plans, permits obtained from the Town of Oro Valley, to the preconstruction meeting, months have passed. While all the requirements are specifically explained at the preconstruction meeting, issues will arise. Any conflicts should be directed to Dick Holloway, Controlled Access Manager and Construction Site Supervisor through the LRCA Management Office or Gatehouse Attendant.

 

Construction continues on the initial seven units by Pusch Ridge Properties, LLC, in the development of the 49 MirabellaVillas along Pusch Wilderness Drive. Review of architectural details and the Pusch Wilderness Drive interface are ongoing with the Committee. The Mirabella entryway and signage located beyond the North Gate was reviewed by the Committee and has since been completed.

 

The ongoing development of the 237 acres of property known as Ponticello, beyond the North Gate across the bridge by Jack Schoof, Electronic Communities/Benchmark Homes continues. In January 2007, the Committee reviewed conceptual plans for the entry to the bridge; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions. Again in July 2008, the Committee reviewed conceptual plans for additions to the entryway including signage to Ponticello; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions.

 

Discussion pertaining to the Revised Plant List took place at the January 9th, 2007 LRCA Residents’ Council Meeting. Responses from the Community were received and additional details were worked on by La Reserve Residents and the LRAC. The Revised Plant List was approved by the LRCA Board of Directors at the May 19, 2008 Meeting. The Listing will be posted to the La Reserve Websites and incorporated into the LRCA Design Guidelines.

 

 

Date:                       February 27, 2008

To:                          La Reserve Community Association Residents

From:                      La Reserve Architectural Committee

 

Updates since the latest meeting February 27, 2008 are indicated in bold. Postings of new projects for review are being placed by the 12th of the month in the Community Informational Holders at each gate location as well as some additional holders within several Subdivisions of the Community. This information is also available on the La Reserve Website.

 

The following projects are currently under review as of February 27, 2008:

                Lot 3       Wilderness Estates I                           final plans approved 11-01-06/pending preconstruction meeting

                Lot 13     Wilderness Estates I                           ongoing home construction projects

                Lot 27     Wilderness Estates II                          preconstruction meeting 08-16-06/in final stages of completion

                Lot 30     Wilderness Estates II                          final plans approved 01-01-06/pending preconstruction meeting

                Lot 33     Wilderness Estates II                          preconstruction meeting 09-27-06/in final stages of completion

                Lot 38     Wilderness Estates II                          final plans approved July 2007 for garage/carriage house & outdoor areas                                                                                                                              including pool

                Lot 42     Wilderness Estates II                          preliminary plans approved December 2006

                Lot 14     Wilderness Estates III                         modified preliminary plans approved 01-09-08

                Lot 17     Wilderness Estates III                         preconstruction meeting 10-25-06/stucco completed

                Lot 34     Wilderness Estates III                         Resident occupied/awaiting post construction completion

                Lot 36     Wilderness Estates III                         Resident occupied/awaiting post construction inspection

                Lot 52     Wilderness Estates III                         preconstruction meeting 09-01-06

                                                                                                Resident occupied/awaiting post construction inspection

                Lot 56     Wilderness Estates III                         construction postponed indefinitely/potentially 2008

                Lot 4T    Wilderness Estates III                         preliminary plans approved September 2007

                Lot 13     Bighorn Point                                       preconstruction meeting 03-05-07/completed post construction inspection                                                                                                              pending administrative followup      

Desert Point Retirement Center                         final plans approved for Phase 2 to the existing 3-story assisted living facility/51 additional units will be added with improvements to the entry, parking, pool, and common areas/preconstruction meeting 06-27-07/ construction in progress

 

It is important to note the amount of time that evolves from submittal to the beginning of new construction varies. While postings of projects for review are timely, from approval of final plans, permits obtained from the Town of Oro Valley, to the preconstruction meeting, months have passed. While all the requirements are specifically explained at the preconstruction meeting, issues will arise. Any conflicts should be directed to Dick Holloway, Controlled Access Manager and Construction Site Supervisor through the LRCA Management Office or Gatehouse Attendant.

 

Construction continues on initial seven units by Pusch Ridge Properties, LLC, in the development of the 49 condominium units along Pusch Wilderness Drive. Changes to the final plat approved  by the Town of Oro Valley. Review of architectural details and the Pusch Wilderness Drive interface are ongoing with the Committee. The ongoing development of the 237 acres of property beyond the Wilderness III/North Gate across the bridge by Jack Schoof, Electronic Communities/Benchmark Homes continues. Final plat approval of the remaining 101 lots has been received from the Town of Oro Valley. In January 2007, the Committee reviewed conceptual plans for the entry to the bridge; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions.

 

LRCA Legal Counsel has recommended incorporating the Revised Plant List, the Design Review Process Overview, and the LRAC Appeals Process with the La Reserve Design Guidelines. Discussion pertaining to the Revised Plant List took place at the January 9th, 2007 LRCA Residents’ Council Meeting. Responses from the Community have been received and additional details are to be worked on by La Reserve Residents and the LRAC. Further updates will be posted to the La Reserve Websites as this information becomes available.

             

 

 

 

Date:                       January 30, 2008

To:                          La Reserve Community Association Residents

From:                      La Reserve Architectural Committee

 

Updates since the latest meeting January 30, 2008 are indicated in bold. Postings of new projects for review are being placed by the 12th of the month in the Community Informational Holders at each gate location as well as some additional holders within several Subdivisions of the Community. This information is also available on the La Reserve Website.

 

The following projects are currently under review as of January 30, 2008:

                Lot 3       Wilderness Estates I                           final plans approved 11-01-06/pending preconstruction meeting

                Lot 13     Wilderness Estates I                           ongoing home construction projects

                Lot 14     Wilderness Estates I                           holding for final design plans

                Lot 27     Wilderness Estates II                          preconstruction meeting 08-16-06/stucco completed & roof ready to                                                                                                                        install

                Lot 30     Wilderness Estates II                          final plans approved 01-01-06/pending preconstruction meeting

                Lot 33     Wilderness Estates II                          preconstruction meeting 09-27-06/in final stages of completion

                Lot 38     Wilderness Estates II                          final plans approved July 2007 for garage/carriage house & outdoor areas                                                                                                                              including pool

                Lot 42     Wilderness Estates II                          preliminary plans approved December 2006

                Lot 14     Wilderness Estates III                         modified preliminary plans approved 01-09-08

                Lot 17     Wilderness Estates III                         preconstruction meeting 10-25-06/stucco prep in progress

                Lot 34     Wilderness Estates III                         Resident occupied/awaiting post construction completion

                Lot 36     Wilderness Estates III                         Resident occupied/awaiting post construction inspection

                Lot 52     Wilderness Estates III                         preconstruction meeting 09-01-06

                                                                                                Resident occupied/awaiting post construction inspection

                Lot 56     Wilderness Estates III                         construction postponed indefinitely/potentially 2008

                Lot 4T    Wilderness Estates III                         preliminary plans approved September 2007

                Lot 13     Bighorn Point                                       preconstruction meeting 03-05-07/completed pending post                                                                                                                                         construction inspection     

Lot 30     La Mirada                                              home addition completed pending/post construction inspection

Desert Point Retirement Center                         final plans approved for Phase 2 to the existing 3-story assisted living facility/51 additional units will be added with improvements to the entry, parking, pool, and common areas/preconstruction meeting 06-27-07/framing in progress

 

It is important to note the amount of time that evolves from submittal to the beginning of new construction varies. While postings of projects for review are timely, from approval of final plans, permits obtained from the Town of Oro Valley, to the preconstruction meeting, months have passed. While all the requirements are specifically explained at the preconstruction meeting, issues will arise. Any conflicts should be directed to Dick Holloway, Controlled Access Manager and Construction Site Supervisor through the LRCA Management Office or Gatehouse Attendant.

 

Framing for initial seven units in progress by Pusch Ridge Properties, LLC, in the development of the 49 condominium units along Pusch Wilderness Drive. Changes to the final plat approved  by the Town of Oro Valley. Review of architectural details and the Pusch Wilderness Drive interface are ongoing with the Committee. The ongoing development of the 237 acres of property beyond the Wilderness III/North Gate across the bridge by Jack Schoof, Electronic Communities/Benchmark Homes continues. Final plat approval of the remaining 101 lots has been received from the Town of Oro Valley. In January 2007, the Committee reviewed conceptual plans for the entry to the bridge; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions.

 

LRCA Legal Counsel has recommended incorporating the Revised Plant List, the Design Review Process Overview, and the LRAC Appeals Process with the La Reserve Design Guidelines. Discussion pertaining to the Revised Plant List took place at the January 9th, 2007 LRCA Residents’ Council Meeting. Responses from the Community have been received and additional details are to be worked on by La Reserve Residents and the LRAC. Further updates will be posted to the La Reserve Websites as this information becomes available.

             

              

Date:                       January 9, 2008

To:                          La Reserve Community Association Residents

From:                      La Reserve Architectural Committee

 

Updates since the latest meeting January 9, 2008 are indicated in bold. Postings of new projects for review are being placed by the 12th of the month in the Community Informational Holders at each gate location as well as some additional holders within several Subdivisions of the Community. This information is also available on the La Reserve Website.

 

The following projects are currently under review as of January 9, 2008:

                Lot 3       Wilderness Estates I                           final plans approved 11-01-06/pending preconstruction meeting

                Lot 13     Wilderness Estates I                           ongoing home construction projects

                Lot 14     Wilderness Estates I                           holding for final design plans

                Lot 27     Wilderness Estates II                          preconstruction meeting 08-16-06/stucco completed & roof ready to                                                                                                                         install

                Lot 30     Wilderness Estates II                          final plans approved 01-01-06/pending preconstruction meeting

                Lot 33     Wilderness Estates II                          preconstruction meeting 09-27-06/in final stages of completion

                Lot 38     Wilderness Estates II                          final plans approved July 2007 for garage/carriage house & outdoor areas                                                                                                                            including pool

                Lot 42     Wilderness Estates II                          preliminary plans approved December 2006

                Lot 14     Wilderness Estates III                         modified preliminary plans approved 01-09-08

                Lot 17     Wilderness Estates III                         preconstruction meeting 10-25-06/stucco prep in progress

                Lot 34     Wilderness Estates III                         Resident occupied/awaiting post construction completion

                Lot 36     Wilderness Estates III                         Resident occupied/awaiting post construction inspection

                Lot 52     Wilderness Estates III                         preconstruction meeting 09-01-06

                                                                                                Resident occupied/awaiting post construction inspection

                Lot 56     Wilderness Estates III                         construction postponed indefinitely/potentially 2008

                Lot 4T    Wilderness Estates III                         preliminary plans approved September 2007

                Lot 13     Bighorn Point                                       preconstruction meeting 03-05-07/completed pending post                                                                                                                                         construction inspection     

Lot 30     La Mirada                                              home addition completed pending/post construction inspection

Desert Point Retirement Center                         final plans approved for Phase 2 to the existing 3-story assisted living facility/51 additional units will be added with improvements to the entry, parking, pool, and common areas/preconstruction meeting 06-27-07/framing in progress

 

It is important to note the amount of time that evolves from submittal to the beginning of new construction varies. While postings of projects for review are timely, from approval of final plans, permits obtained from the Town of Oro Valley, to the preconstruction meeting, months have passed. While all the requirements are specifically explained at the preconstruction meeting, issues will arise. Any conflicts should be directed to Dick Holloway, Controlled Access Manager and Construction Site Supervisor through the LRCA Management Office or Gatehouse Attendant.

 

Framing for initial seven units in progress by Pusch Ridge Properties, LLC, in the development of the 49 condominium units along Pusch Wilderness Drive. Changes to the final plat approved  by the Town of Oro Valley. Review of architectural details and the Pusch Wilderness Drive interface are ongoing with the Committee. The ongoing development of the 237 acres of property beyond the Wilderness III/North Gate across the bridge by Jack Schoof, Electronic Communities/Benchmark Homes continues. Final plat approval of the remaining 101 lots has been received from the Town of Oro Valley. In January 2007, the Committee reviewed conceptual plans for the entry to the bridge; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions.

 

LRCA Legal Counsel has recommended incorporating the Revised Plant List, the Design Review Process Overview, and the LRAC Appeals Process with the La Reserve Design Guidelines. Discussion pertaining to the Revised Plant List took place at the January 9th, 2007 LRCA Residents’ Council Meeting. Responses from the Community have been received and additional details are to be worked on by La Reserve Residents and the LRAC. Further updates will be posted to the La Reserve Websites as this information becomes available.

 

 

 

Date:                       October 31, 2007

To:                          La Reserve Community Association Residents

From:                      La Reserve Architectural Committee

 

Updates since the latest meeting October 31, 2007 are indicated in bold. Postings of new projects for review are being placed by the 12th of the month in the Community Informational Holders at each gate location as well as some additional holders within several Subdivisions of the Community. This information is also available on the La Reserve Website.

 

The following projects are currently under review as of October 31, 2007:

                Lot 3       Wilderness Estates I                           final plans approved 11-01-06/pending preconstruction meeting

                Lot 13     Wilderness Estates I                           ongoing home construction projects

                Lot 14     Wilderness Estates I                           holding for final design plans

                Lot 27     Wilderness Estates II                          preconstruction meeting 08-16-06/stucco prep in progress & roof ready to                                                                                                                install

                Lot 30     Wilderness Estates II                          final plans approved 01-01-06/pending preconstruction meeting

                Lot 33     Wilderness Estates II                          preconstruction meeting 09-27-06/stucco with color in progress

                Lot 38     Wilderness Estates II                          final plans approved for garage/carriage house & outdoor areas                                                                                                                                  including pool

                Lot 42     Wilderness Estates II                          preliminary plans approved

                Lot 14     Wilderness Estates III                         preliminary plans denied due to setback noncompliance

                Lot 17     Wilderness Estates III                         preconstruction meeting 10-25-06/framing in progress

                Lot 18     Wilderness Estates III                         ongoing home construction improvements from January 2006/post construction                                                                                                      inspection completed

                Lot 34     Wilderness Estates III                         Resident occupied/awaiting post construction completion

                Lot 36     Wilderness Estates III                         preconstruction meeting 10-30-06/stucco completed

                Lot 52     Wilderness Estates III                         preconstruction meeting 09-01-06

                                                                                                   Resident occupied/awaiting post construction inspection

                Lot 56     Wilderness Estates III                         construction postponed indefinitely/potentially 2008

                Lot 4T    Wilderness Estates III                         preliminary plans approved

                Lot 13     Bighorn Point                                       preconstruction meeting 03-05-07/completed pending post                                                                                                                                         construction inspection     

Lot 18     La Mirada                                              final plans for addition approved/valid until May 2007

Lot 30     La Mirada                                              home addition completed pending post construction inspection

Desert Point Retirement Center                         final plans approved for Phase 2 to the existing 3-story assisted living facility/51 additional units will be added with improvements to the entry, parking, pool, and common areas/preconstruction meeting 06-27-07/framing in progress

 

It is important to note the amount of time that evolves from submittal to the beginning of new construction varies. While postings of projects for review are timely, from approval of final plans, permits obtained from the Town of Oro Valley, to the preconstruction meeting, months have passed. While all the requirements are specifically explained at the preconstruction meeting, issues will arise. Any conflicts should be directed to Dick Holloway, Controlled Access Manager and Construction Site Supervisor through the LRCA Management Office or Gatehouse Attendant.

 

Framing for initial seven units in progress by Pusch Ridge Properties, LLC, in the development of the 49 condominium units along Pusch Wilderness Drive. Changes to the final plat approved  by the Town of Oro Valley. Review of architectural details and the Pusch Wilderness Drive interface are ongoing with the Committee. The ongoing development of the 237 acres of property beyond the Wilderness III/North Gate across the bridge by Jack Schoof, Electronic Communities/Benchmark Homes continues. Final plat approval of the remaining 101 lots has been received from the Town of Oro Valley. In January 2007, the Committee reviewed conceptual plans for the entry to the bridge; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions.

 

LRCA Legal Counsel has recommended incorporating the Revised Plant List, the Design Review Process Overview, and the LRAC Appeals Process with the La Reserve Design Guidelines. Discussion pertaining to the Revised Plant List took place at the January 9th, 2007 LRCA Residents’ Council Meeting. Responses from the Community have been received and additional details are to be worked on by La Reserve Residents and the LRAC. Further updates will be posted to the La Reserve Websites as this information becomes available.

 

Date:                       September 26, 2007

To:                          La Reserve Community Association Residents

From:                      La Reserve Architectural Committee

 

Updates since the latest meeting September 26, 2007 are indicated in bold. Postings of new projects for review are being placed by the 12th of the month in the Community Informational Holders at each gate location as well as some additional holders within several Subdivisions of the Community. This information is also available on the La Reserve Website.

 

The following projects are currently under review as of September 26, 2007:

                Lot 3       Wilderness Estates I                           final plans approved 11-01-06/pending preconstruction meeting

                Lot 13     Wilderness Estates I                           ongoing home construction projects

                Lot 14     Wilderness Estates I                           holding for final design plans

                Lot 25     Wilderness Estates II                          plans to build withdrawn/hydroseeding completed

                Lot 27     Wilderness Estates II                          preconstruction meeting 08-16-06/stucco prep in progress

                Lot 30     Wilderness Estates II                          final plans approved 01-01-06/pending preconstruction meeting

                Lot 33     Wilderness Estates II                          preconstruction meeting 09-27-06/stucco prep in progress

                Lot 38     Wilderness Estates II                          final plans approved for garage/carriage house & outdoor areas                                                                                                                               including pool

                Lot 42     Wilderness Estates II                          preliminary plans approved

                Lot 14    Wilderness Estates III                       preliminary plans denied due to setback noncompliance

                Lot 17     Wilderness Estates III                         preconstruction meeting 10-25-06/framing in progress

                Lot 18     Wilderness Estates III                         ongoing home construction improvements from January 2006/post construction                                                                                                   inspection completed

                Lot 34     Wilderness Estates III                         Resident occupied/awaiting post construction completion

                Lot 36     Wilderness Estates III                         preconstruction meeting 10-30-06/stucco prep in progress

                Lot 52     Wilderness Estates III                         preconstruction meeting 09-01-06

                                                                                                Resident occupied/awaiting post construction inspection

                Lot 56     Wilderness Estates III                         construction postponed indefinitely/potentially 2008

                Lot 4T    Wilderness Estates III                         preliminary plans approved

                Lot 13     Bighorn Point                                       preconstruction meeting 03-05-07/in final stages of

                                                                                                completion          

Lot 18     La Mirada                                              final plans for addition approved/valid until May 2007

Lot 30     La Mirada                                              final plans for home addition approved/stucco prep in progress

Desert Point Retirement Center                         final plans approved for Phase 2 to the existing 3-story assisted living facility/51 additional units will be added with improvements to the entry, parking, pool, and common areas/preconstruction meeting 06-27-07/foundation in progress

 

It is important to note the amount of time that evolves from submittal to the beginning of new construction varies. While postings of projects for review are timely, from approval of final plans, permits obtained from the Town of Oro Valley, to the preconstruction meeting, months have passed. While all the requirements are specifically explained at the preconstruction meeting, issues will arise. Any conflicts should be directed to Dick Holloway, Controlled Access Manager and Construction Site Supervisor through the LRCA Management Office or Gatehouse Attendant.

 

Excavation and the installation of utilities continues by Pusch Ridge Properties, LLC, in the development of the 49 condominium units along Pusch Wilderness Drive. Changes to the final plat approved  by the Town of Oro Valley. Footings in progress for initial seven units. Review of architectural details and the Pusch Wilderness Drive interface are ongoing with the Committee. The ongoing development of the 237 acres of property beyond the Wilderness III/North Gate across the bridge by Jack Schoof, Electronic Communities/Benchmark Homes continues. Final plat approval of the remaining 101 lots has been received from the Town of Oro Valley. In January 2007, the Committee reviewed conceptual plans for the entry to the bridge; approved the project from the visual architectural aspect; and made recommendations to the Board of Directors regarding development of the intersection, public safety, and compliance with Oro Valley regulatory conditions.

 

LRCA Legal Counsel has recommended incorporating the Revised Plant List, the Design Review Process Overview, and the LRAC Appeals Process with the La Reserve Design Guidelines. Discussion pertaining to the Revised